Restoration
consisted of the construction of in-stream rock structures, root wads, bank
grading and channel grading. The stream pattern was slightly altered between
1+00 and 2+00 to improve the meander radius to a stable geometry.
Structures
Installed
(6) Root wads
(2) Rock vanes
(3) J hook vanes
(1) Cross vane
302 feet of rock toe protection
493 feet of bank grading
1042 feet of high tensile wire stream bank fencing